Name of project : Equipment and piping installation work for methyl ester and fatty alcohol plant
Location : Thai Oleochemicals Co., Ltd (Hemaraj Industrial Estate, Mabtaphud, Rayong, Thailand)
Owner : Thai Oleochemicals Co., Ltd.
Client : Shedden Uhde (Thailand) Ltd.
Work description :
Piping installation
- Fabrication, erection, hydrostatic test of process, and utilization of piping work for Methyl Ester Plant (99,000 DB) and Fatty Alcohol Plant (89,000 DB). Piping consisted of 45% of C.S pipe, 50% of SUS 304L pipe, 4% of SUS 316 Ti and 1% of alloy pipe (P22)
- Supply, fabrication and erection of 225 tons steel pipe supports
Equipment installation
- Erection of rotating, equipment and static equipment at 300 tons in total
All painting work (sandblasting to top coat) : approximate = 20,000 m2
Contract value (Baht) : 217,291,340.47
Duration : February 8, 2007 – March 15, 2008 (Methyl ester plant had to be completed by November 30, 2007 but it was completed 3 weeks before schedule)
Scope of work : Piping materials and equipment were supplied by the client, others were supplied by K Thai.
Maximum No. of workers : 988 people at peak period
Total man-hours : 1,000,000 man-hr for direct workers only
Process piping work and equipment installation